FMEA: Failure Mode and Effects Analysis, Part 1

The Editor's Desk
by
1
Share Facebook X LinkedIn WhatsApp Email

Failure Mode and Effects Analysis (FMEA) is a structured way to list the ways a product or process could fail, judge how serious each failure would be, and decide which ones to fix first. It is widely used in manufacturing at every phase of the product life cycle. A failure cause is any error or defect in a process, design or item, especially one that affects the customer, and it can be potential or actual. Effects analysis means studying the consequences of those failures.

In this article we look at why the semiconductor industry needs FMEA, and how it saves cost and customers while protecting the company's bottom line.

FMEA in plain words

An FMEA is a team exercise captured in a table. For each part of a design or each step of a process, the team asks three questions: how could this fail, what would happen if it did, and why would it happen? Each failure is then scored, and the highest risks get actions: a design change, an extra test, a better process control. The table is kept and updated, so it becomes a record of what the company knows about its risks.

FMEA works best early. Used during design, it helps avoid failures before they are built in. Later it supports process control, before and during production. Ideally it starts at the earliest concept stage and continues for the life of the product or service.

Key terms

  • Failure mode: the way a failure is observed; it describes how the failure occurs.
  • Failure effect: the immediate consequence of a failure on the operation, function or status of an item.
  • Local effect: the failure effect on the item being analyzed.
  • Next higher level effect: the failure effect at the next higher indenture level.
  • End effect: the failure effect at the highest indenture level, the whole system.
  • Failure cause: a defect in design, process, quality or part application that is the underlying cause of the failure, or that starts a process leading to failure.
  • Severity: how bad the consequences of a failure mode are. It considers the worst potential consequence, judged by the degree of injury, property damage or system damage that could result.
  • Indenture levels: a way of describing item complexity in a hierarchy (system, subsystem, assembly, part). Complexity increases as the level number gets closer to one.

History and background

The US military developed the FMEA process in 1949 to classify failures by their impact on mission success and on the safety of personnel and equipment. FMEA was later used in the 1960s Apollo space program. In the automotive industry, Ford adopted it to reduce risk after the Pinto, whose design flaw failed to prevent the fuel tank from rupturing in a crash, with a risk of fire. FMEA is used in many formal quality systems, such as QS-9000 and ISO/TS 16949 in the automotive industry, which matters to every semiconductor company that sells chips for cars.

Why semiconductor companies use FMEA

  1. If the products come back, the customers will not.
  2. FMEA checks whether the product meets its requirements before tape-out or delivery.
  3. It saves research and development cost and avoids re-designs.

Strengths and limits in brief

FMEA is a bottom-up method: it starts from parts and asks what each failure does to the system. That makes it thorough for single failures, but it can miss failures that only happen when several things go wrong together. Fault tree analysis (FTA), a top-down method that starts from an unwanted system event, complements it. The scoring scheme also has known weaknesses, covered in the deep dive.

Deep dive: the numbers and details

This part holds the scoring scales, a worked RPN example, the newer Action Priority method and the full semiconductor checklist. Skip it if the overview is all you need.

Scoring: severity, occurrence and detection

In most formal FMEA systems, each failure is rated on three scales:

  • Severity (S): how serious the effect is.
  • Occurrence (O): how likely the cause is to happen. This is also often called probability (P).
  • Detection (D): how likely current controls are to miss the problem before it reaches the customer.

A simple scheme uses three scales from 1 (lowest risk) to 10 (highest risk). Note that detection runs the opposite way to what the word suggests: D = 1 means the control is certain to detect the problem, and D = 10 means it is certain not to detect it, or that no control exists. The overall risk of each failure is the Risk Priority Number:

RPN = S × O × D

The RPN ranges from 1 to 1,000 and is used to rank failures and decide on actions, usually by reducing the chance of occurrence and by improving controls that detect the failure.

Worked example: an RPN table for a mixed-signal chip

Illustrative ratings for three failure modes:

ItemFailure modeEffectSODRPN
Power-on resetReset releases before supply is stableDevice starts in an unknown state846192
Serial I/O blockHold violation at fast cornerIntermittent data errors in the field735105
Bond padInsufficient ESD protectionDamage during board assembly92354

The team acts on the power-on reset first. Suppose they add a supply monitor (O falls from 4 to 2) and a new production test at low supply ramp rate (D falls from 6 to 3). The new RPN is 8 × 2 × 3 = 48. Severity stays at 8, because only a design change to the effect itself can lower severity.

Why RPN can mislead

Multiplying the three ratings can cause rank reversals, where a less serious failure mode gets a higher RPN than a more serious one. The ratings are ordinal numbers: they say one rating is worse than another, but not by how much. A rating of 2 is not necessarily twice as bad as 1, and 8 is not necessarily twice as bad as 4, but multiplication treats them as if they were.

A concrete case: failure A with S = 10, O = 2, D = 2 has RPN 40. Failure B with S = 4, O = 4, D = 4 has RPN 64. B ranks higher, even though A could injure someone and B cannot. Many teams therefore add a rule that any failure with severity 9 or 10 is acted on regardless of RPN.

The newer method: Action Priority

The AIAG and VDA FMEA Handbook, published jointly by the US and German automotive industry groups, replaced the AIAG 4th edition and the VDA Volume 4 manuals and dropped RPN in favor of Action Priority (AP). AP uses lookup tables covering all 1,000 combinations of S, O and D, giving severity the most weight, then occurrence, then detection, and assigns each combination a priority of High, Medium or Low. The handbook also defines seven steps: planning and preparation, structure analysis, function analysis, failure analysis, risk analysis, optimization and results documentation. A summary is available from Quality-One: AIAG and VDA FMEA.

The automotive quality standard has moved on too: IATF 16949:2016 cancels and replaces ISO/TS 16949:2009, so new automotive FMEA work is done under IATF 16949 and the AIAG and VDA handbook.

Other limits of FMEA

  • Used as a top-down tool, FMEA may only find the major failure modes in a system. Fault tree analysis is better suited to top-down analysis.
  • Used bottom-up, FMEA can complement FTA and find many more causes and failure modes that lead to top-level symptoms.
  • It does not handle complex failure modes that involve several failures within a subsystem well.
  • It does not by itself give expected failure intervals for particular failure modes at the subsystem or system level; that needs reliability data and models.

Which type of FMEA?

  1. System FMEA
    • Customer interface: talk to the customer and get as much information as possible about the product.
    • Project resources: analyze the resources available for execution and delivery.
    • Architecture: study the architecture as thoroughly as possible in a group brainstorming session.
  2. Design or technology FMEA
    • Mechanical or electrical
    • Technology
    • Software
  3. Fab or assembly (process) FMEA
    • Mechanical
    • Electrical
    • Testing

What counts as a failure?

  1. A re-design
  2. A failed test case
  3. Any crash
  4. All errata sheets
  5. All bugs
  6. All change requests
  7. All field failures
  8. All failure analysis requests (FARs) and returns (RMAs)
  9. All test programs that did not work right the first time
  10. Any project started without requirements defined by marketing, or not accepted by the customer

Teams and roles

  1. Facilitator: the quality engineer.
  2. Project group: architect, programmers, RTL designers, test, quality and marketing.
  3. Support group: representatives from test departments, application engineers and sales.

Be specific

  1. Define the scope of the FMEA and draw a picture of it:
    • for example, the serial I/O block;
    • refer to a block diagram of the product;
    • provide customer and market requirement documents, by version;
    • provide the bill of materials (BOM) for the product;
    • make sure the team includes all cross-functional departments.
  2. Create clear visual definitions of the FMEA scope. This usually takes extensive whiteboard sessions.
  3. Start with the three riskiest and the newest features. Be as specific as possible, using a product brief or a data sheet.

To be continued in Part 2.

Further reading

The Editor's Desk
About the Author
The Editor's Desk
Share Facebook X LinkedIn WhatsApp Email

Post a Comment

1 Comments

Your comments will be moderated before it appears here.

  1. A respectable technical article is NOT a soap opera with an ending of "to be continued"