TSMC told investors in January 2026 that advanced packaging was slightly over 10% of its 2025 revenue, which on US$122.42 billion of total revenue is a little over US$12 billion. Amkor reported US$6.71 billion of total net sales for the same year, and ASE said its leading-edge packaging and test line, LEAP, reached US$1.6 billion. These categories are defined differently, so they do not rank anyone, but they do show that packaging is now a business of real size inside a foundry.
The old line, where the foundry made the wafer and an outsourced assembly and test house (OSAT) did everything afterwards, no longer describes how these parts get built. Ownership now changes hands step by step, and sometimes crosses back. This post maps each step to who does it, using what the companies themselves publish, and then shows with a small worked example why the choice matters to a buyer.
Key takeaways
- "Foundry or OSAT" is the wrong question for a 2.5D or 3D part. The useful question is who owns each step, and who pays when a package fails at that step.
- Wafer-level stacking is the step that stays closest to the foundry. Bumping, assembly, substrate attach and test are all offered by both camps.
- The crossings are public. TSMC plans to contract turnkey packaging and test from Amkor in Arizona, Amkor plans to run Intel's EMIB assembly, and Samsung's turnkey page names OSAT partners.
- In our illustrative example, materials make up about 90% of the cost of each package started. A contract term on scrap can matter more than the assembly fee.
The lines have moved in both directions
Start with what each company says it sells. All of this is company-published description, not independent verification.
| Company | What it publishes | Where the line crosses |
|---|---|---|
| TSMC | Describes SoIC as frontend 3D stacking and CoWoS as a chip-last process on an interposer, with CoWoS-S, CoWoS-L and CoWoS-R variants and InFO alongside | In October 2024 it signed a memorandum to contract turnkey packaging and test from Amkor in Peoria, Arizona. In April 2026 its CEO said its packaging capacity is very tight and it has to work with OSAT partners |
| Intel Foundry | Lists EMIB 2.5D and 3.5D, Foveros-S, Foveros-R (stated as production ready in 2027) and Foveros Direct 3D | Says chips can go through its own assembly and test or through an OSAT. Test ranges from full turnkey to support for customer-owned programmes and hardware |
| Samsung Foundry | Describes a package turnkey service across fab, bump, package and test, with I-Cube 2.5D derivatives | States it can enable in-house or OSAT routes, and lists Amkor, JCET, ASE Korea and Hana Micron as OSAT partners |
| Amkor | Lists wafer bump, wafer probe, back-grind, package design, packaging, burn-in, system-level and final test, and drop shipment as turnkey services | Announced in April 2025 that it will implement Intel EMIB assembly in Korea, Portugal and its planned Arizona site. Its 10-K describes foundries offering turnkey services through to final test as competitors |
| ASE | Its VIPack platform covers FOCoS, FOCoS-Bridge, FOPoP, FOSiP, TSV-based 2.5D and 3D processing and co-packaged optics | Reports LEAP as a separate line. In February 2026 it guided to about US$3.2 billion for the year, split roughly 75% packaging and 25% testing, and in July it said it was tracking ahead of a US$3.5 billion figure |
Two things stand out. First, the foundries openly offer an OSAT route while OSATs openly plan to run technology that began at a foundry. Second, Amkor's 10-K treats contract foundries as both customers and rivals: it says that foundry and integrated device customers keep weighing outsourced services against their own in-house capacity.
TSMC's position in late 2026 is worth reading closely. On its October call, its CEO claimed real production at 5 times reticle size, doubted that anyone else can do that today, and described work towards 9 times and 14 times. TSMC's technology page says a 5.5 times interposer solution finished certification in 2025 with volume production to start in 2026. These are TSMC's own statements, and we have not verified them independently. Asked in April whether TSMC would let another company package wafers it makes, the CEO gave no direct yes or no, saying instead that competitors offer attractive technology, that customers can have more choices, and that TSMC would not leave business on the table.
The ownership map, step by step
This is a generic flow for a logic and HBM part on an interposer or bridge. Real flows vary by technology, and some reorder these steps. The "published" columns cite what companies say they offer. The last column is our reading of what a buyer needs to pin down, and it is advice rather than sourced fact.
| Step | Foundry route (published) | OSAT route (published) | What the buyer should settle |
|---|---|---|---|
| 1. Wafer fabrication | Foundry | Not offered by the OSATs covered here | Whether the foundry will ship wafers to an outside packager for your product, and on what terms |
| 2. Wafer-level 3D stacking | TSMC SoIC (called frontend stacking), Intel Foveros Direct, Samsung vertical integration | ASE lists TSV-based 3D IC processing. Ask what bond pitch and bond type are actually qualified | This step is closest to the fab. Moving it later is usually a redesign rather than a sourcing change |
| 3. Wafer probe and sort | Intel lists wafer sort and die sort. Samsung lists wafer test | Amkor lists wafer probe | Who owns the probe programme, the data and the pass limits that define a known good die |
| 4. Bumping and back-grind | Samsung lists C4, copper pillar and microbump | Amkor lists wafer bump and back-grind | Bump metallurgy and pitch must match the assembly site, so fix this before choosing the next step |
| 5. Interposer or bridge supply | Samsung lists interposer under fab. Intel offers EMIB. TSMC offers CoWoS variants | ASE lists FOCoS-Bridge and TSV-based 2.5D. Amkor's EMIB work uses Intel's bridge technology | Who sources the silicon, and whether a second source can use the same design |
| 6. Die and HBM attach | TSMC CoWoS and InFO, Intel EMIB and Foveros, Samsung I-Cube assembly | Amkor and ASE, plus Amkor's planned EMIB assembly | Who buys the HBM, who holds it in stock, and who pays if a good stack is lost to a bad attach |
| 7. Substrate attach | Samsung describes supply control of PCB suppliers and pre-booking capacity under long-term agreements | Amkor says it sources laminate substrates from a limited group of suppliers | Who holds the substrate allocation. It can gate output as hard as the packaging line itself |
| 8. Burn-in, final and system-level test | Intel lists burn-in, final test and system-level test. Samsung lists package test | Amkor lists burn-in, system-level and final test | Where test lives, and whether results feed back to steps 3 and 6 in time to change anything |
| 9. Shipment | Part of a turnkey offer, in the terms each provider agrees | Amkor lists drop shipment | Where title passes, and who holds the finished stock |
If the earlier steps are unfamiliar, our posts on how wafer probe keeps bad dies out of costly packaging and on what silicon interposers do in a 2.5D package cover them in more depth.
What this means for buyers
You are choosing an accountability model
A single turnkey owner gives you one party to call when a part fails. A split flow gives you more choice and more interfaces, and each interface is a place where a failure can land between two contracts. Neither is the right answer in every case. What goes wrong is drifting into a split flow without deciding who owns the failure analysis across the seams.
Capacity is a technical constraint
TSMC's CEO said in April that its capacity is tight and it needs OSAT partners, and in January TSMC said it was applying for permits for its first advanced packaging fab in Arizona. Amkor says construction of its Arizona facility began in the second half of 2025, and it put its 2026 capital spending at about US$2.5 billion in October. So the location of the fab and the location of the packaging may not match for some time. If US assembly matters to your programme, ask for dates in writing. Amkor's EMIB announcement gives no start dates, so confirm the qualification status at each site rather than inferring it from the press release.
Choosing a route is also choosing a design kit
CoWoS, EMIB, I-Cube and FOCoS are not interchangeable. Switching partly means re-doing floorplan, power delivery and thermal work, as our comparison of EMIB and CoWoS trade-offs shows. A second source for the assembly labour is much easier to arrange than a second source for the architecture. Our chiplet lifecycle on The Semiconductor Hub shows where these choices fall in a programme.
Test can move separately
ASE's guidance implies about a quarter of its 2026 LEAP revenue from testing, which on US$3.2 billion is about US$0.8 billion. TSMC's January capital plan set aside about 10% to 20% of the 2026 budget for advanced packaging, testing, mask making and others, a basket that its CFO put at about or below 10% in the past. For a buyer, the point is that test can be separated from assembly, and Intel explicitly offers support for customer-owned test programmes. Decide early who owns the programme and the data, because that is hard to move later.
A worked example: the fee is the small number
Every number here is an illustrative assumption, not a quote or data from any company. The two routes and their yields are invented to show the method. Nothing here implies that either kind of supplier yields better. Replace them with your own figures.
| Per package started (illustrative) | Route A: one turnkey owner | Route B: split flow |
|---|---|---|
| Tested compute dies | US$300 | US$300 |
| HBM set | US$500 | US$500 |
| Interposer and substrate | US$150 | US$150 |
| Assembly and test fee | US$100 | US$80 |
| Extra logistics between sites | US$0 | US$5 |
| Cost per start | US$1,050 | US$1,035 |
| Assembly and test yield | 98% | 96% |
| Cost per good package | US$1,071.43 | US$1,078.13 |
The model assumes a failed package is a total loss, with nothing recovered. Route B starts US$15 cheaper and finishes about US$6.70 dearer per good package, because two points of yield are worth more than the fee saved.
Three checks are worth doing on your own version:
- Break-even yield. Route B matches Route A when its yield reaches 1,035 × 0.98 ÷ 1,050, which is 96.6%. If Route B reached 98% too, it would cost about US$1,056.12 and win.
- Material share. Materials are US$950 of Route A's US$1,050, or about 90%. The party doing the assembly earns the small part of the bill and touches all of it.
- Scrap terms. For 100,000 good packages, Route A needs about 102,041 starts and Route B about 104,167. That is about 2,041 and 4,167 scrapped packages, carrying about US$1.94 million and US$3.96 million of materials. Total spend is about US$107.14 million against US$107.81 million, a gap of about US$0.67 million.
Now suppose Route B's contract refunds half of the scrapped materials, and Route A's refunds nothing. Route B's refund is about US$1.98 million, its total falls to about US$105.83 million, and it now beats Route A by about US$1.31 million. In this example, that one clause moves the result by more than the fee and yield differences, which net to about US$0.67 million. Real terms are private and will differ, so the lesson is about what to negotiate rather than what to expect: get the scrap and consigned-material terms on the table before you compare fees.
Questions to ask before you award the work
- Who owns a failed package at each step? Ask for it in the form of the table above, with a named party in every row.
- Who buys and holds the HBM and the substrates? If it is you, the allocation risk is also yours.
- What defines a known good die, and who signs it off? A dispute after attach is expensive when the pass limits were never agreed.
- Is this site qualified for this technology today? Ask for the qualification report, and treat a future date as a target.
- Who runs failure analysis across a seam? Agree how data moves between companies, and how quickly.
- Will your foundry release wafers for this flow? Get the answer for your product and your volume, rather than relying on general statements.
- Do your location rules cover packaging and test? A US or European wafer may still be assembled elsewhere.
FAQ
Are OSATs losing advanced packaging to foundries?
The published numbers do not show a simple loss. TSMC's packaging share rose from about 8% of revenue in 2024 to slightly over 10% in 2025, and it expects low teens in 2026. Over the same period, ASE's LEAP line went from US$0.6 billion to US$1.6 billion. Both can grow while capacity is short.
Can I compare these revenue figures directly?
No. TSMC's figure is its own advanced packaging category. Amkor's Advanced Products line was US$5.56 billion, or 82.8% of its sales, but it includes flip chip, memory and wafer-level processing with related test, which is far broader than 2.5D and 3D. ASE's LEAP is a separate line, and its definition is not spelled out in the releases we read.
Does a turnkey deal remove the risk?
It moves the risk and makes it easier to trace, but only as far as the contract says. Read the scrap, consigned-material and capacity clauses as closely as the price.
Sources
- TSMC, Q4 2025 earnings call transcript, 15 January 2026; Q1 2026 transcript, 16 April 2026; Q3 2026 transcript, 15 October 2026 (LSEG edited transcripts on TSMC's investor site).
- TSMC, 2025 Annual Report, letter to shareholders (revenue and technology summary).
- TSMC, "HPC Wafer Level System Integration" technology page, read 7 November 2026.
- TSMC and Amkor, "Amkor and TSMC to Expand Partnership and Collaborate on Advanced Packaging in Arizona", 4 October 2024.
- Intel Foundry, "Redefine Compute Through Packaging Innovations" packaging page, read 7 November 2026.
- Samsung Foundry, Package Turnkey Service, Advanced Packaging and Foundry overview pages, and the tech blog post "Samsung Advanced Packaging Helps Customers Bring Their Own Architecture" (undated), read 7 November 2026. The turnkey, advanced packaging and blog pages carry a notice about page availability, so confirm their currency with Samsung.
- Amkor Technology, Form 10-K for 2025, filed 20 February 2026; Q3 2026 results release, 26 October 2026.
- Amkor Technology, "Amkor-Intel Partnership Expands EMIB Packaging Capacity", 30 April 2025.
- ASE Technology Holding, Q4 2025 earnings release (Form 6-K, 5 February 2026) and Q2 2026 earnings release (Form 6-K, 30 July 2026).
- ASE, "ASE introduces VIPack to help transform packaging solution enablement", 1 June 2022.
The worked example uses illustrative numbers. Vendor figures and statements are the companies' own claims and targets, as published on the dates shown, and dollar figures derived from a stated share are our arithmetic. This post is general information for engineering and sourcing decisions and is not investment advice.